The Chhattisgarh forest department has registered a Preliminary Offence Report (POR) against a senior National Mineral Development Corporation (NMDC) official after a mining waste dump collapsed in Dantewada district on November 18, officials said on Friday. A preliminary assessment indicates damage to 25-30 hectares of forest land, and the department is assessing the ecological damage and could impose a penalty of up to ₹2.5 crore. "We have registered a case against the general manager (GM) of the NMDC and investigation will follow," principal chief conservator of forests (PCCF) Arun Pandey said.
Divisional forest officer (DFO), Dantewada, Ranganadha Ramakrishna said the debris spread over nearly three kilometres and the department was counting trees in 100-square-metre plots on both sides to determine how many were buried, with similar sampling planned at six to seven locations. The department estimates a penalty of around ₹2 crore if 25 hectares are affected and up to ₹2.5 crore if damage extends to 30 hectares, he said, adding that dense forests have around 260 to 271 trees per hectare.
In a statement, NMDC said a portion of an old waste dump at Deposit-14 had collapsed due to natural geological activity, and claimed the origin was in a forest area outside its mining lease, around two kilometres west of the lease area. The company said waste material spread around 200 to 250 metres while soil and gravel debris travelled two to three kilometres, and that a January 2026 study by the Central Institute of Mining and Fuel Research (CIMFR), Dhanbad, had found the dump stable. Local residents, however, estimated the debris spread over 8-10 km in length and 300-500 metres in width, though the extent of damage was yet to be assessed.
Ramakrishna said the department will also issue notices to NMDC over the latest incident and a similar landslide in 2024, which damaged around four hectares of forest and drew a ₹10 crore fine that the company has not paid despite several notices. NMDC said the 2024 incident occurred due to severe floods at Deposit 11C and that it received a notice around three months ago, adding that it is ready to cooperate. The district administration has sought an investigation by IIT Bombay experts, who inspected the site on Wednesday, with a preliminary report expected in 10 to 15 days, Dantewada collector Devesh Kumar Dhruv said.