Chennai Metro Rail Limited has completed the launching of all U-girders on the Koyambedu-Alandur stretch of its phase II project, according to a press release. The corridor, which runs for 14.5 km under the 118.9-km phase II project, is scheduled to be opened next year, and track work on the stretch is also in advanced stages.

U-girders are precast concrete structural beams used in the construction of elevated viaducts, over which trains run. The final U-girder on the stretch was launched on Sunday between Butt Road and Kathipara Junction over Paul Wells Road, using two high-capacity hydraulic cranes. The completed stretch comprises 911 U-girders ranging in length from 15 metres to 33.33 metres, with an average weight of approximately 135 tonnes, the release said. Erecting work was carried out using multiple methods, including launching girders and high-capacity hydraulic cranes, depending on site conditions and location requirements.

The release said the elevated construction faced several challenges, including space constraints and underground and overhead utility lines at locations such as Kaliamman Koil Street, Butt Road and Paul Wells Road. The integrated flyover along Mount-Poonamallee Road added to the complexity, making girder launching operations particularly challenging.

According to the release, the last girder erected on Sunday at Paul Wells Road was difficult owing to a space crunch, with one of the two high-capacity cranes positioned within nearby church premises and the other placed in a narrow street. For another U-girder at the same location, the Metro Rail had to mobilise an additional 1,000-tonne-capacity crane to complete the work within a tight time frame and in very limited space.